Constuction

Keeping you up-to-date

We provide regular updates on Cycle Enfield construction works occurring across the borough. Click the drop-downs below to read more on each project.

A1010 North Scheme

Ordnance Road works

Ordnance Road

Ordnance Road
The junction of Ordnance Road and Hertford Road reopened Thursday 31st October, 3 weeks ahead of schedule. Buses have now diverted back to their normal routes. Works including resurfacing will continue at the junction throughout November.

The letter to residents delivered ahead of the closure of this junction and works is available here.

Nags Head Junction works

Works at this junction are now complete with the new signals activated on Monday 21st October, 3 weeks ahead of schedule.

The notification of works letter delivered to residents in the area is available here.

Help with enquiries

From Monday – Friday between 09:00 – 17:00, Katy Davies, the Public Liaison Officer is available to discuss any construction related queries on 07714 295 768 or cycleenfield@ringwayjacobs.com.

If you have a more general question about Cycle Enfield then use our contact page to get in touch. To report an incident related to Cycle Enfield infrastructure, please complete the form here. If your enquiry is about the Beryl Bikes, please contact the Beryl team at support@beryl.cc.

Minimising Disruption

We know construction can be disruptive. While there are times when it’s unavoidable, we’re working to make the process more manageable. We have explained the ways we’re working in this minimising disruption PDF guide.

Secondary routes

If you have a concern.....

If you have a concern with construction or a more general question about Cycle Enfield then use our contact page to get in touch and we will respond as quickly as possible. To report an incident related to Cycle Enfield infrastructure, please complete the form here.

Minimising disruption

We know construction can be disruptive. While there are times when it’s unavoidable, we’re working to make the process more manageable. We have explained the ways we’re working in this minimising disruption PDF guide.

Firs Lane

New raised parallel crossing has been installed. Footway widened to accommodate 2.5m wide cycle track. New width restriction is in place (just waiting for gate to be installed). High friction surfacing has still be laid on approaches to new crossing.

Barrowell Green

Work is ongoing to widen the existing footpath alongside Clowes Sports Ground to 3m which will become a shared use path for pedestrians and cyclists.