Enfield Logo

WORK'S ABOUT TO START IN YOUR AREA

Safer Travel, Healthier Choices

We’re making improvements to our neighbourhoods and town centres, creating an environment where many more of us can walk or cycle every day.

 

Over the coming weeks and months construction will start around your area. Even though we plan carefully to minimise inconvenience, there could be disruption to your regular routes, so please bear with us whilst we work to make our borough better for everyone. You can see some of the things we’re doing to minimise inconvenience here.

 

Please note this page will be updated as work progresses on each of the respective schemes.  

Ringway Jacobs have appointed a Public Liaison Officer, Rilwan Oshingbade,to assist with any enquiries related to construction, he can be contacted directly on cyclenfield@ringwayjacobs.com

 

If you have an urgent out of hours please call 0844 967 1611 and the team will try to assist wherever possible. Please be aware that non-urgent issues may be redirected to Rilwan to address during normal office hours.

The A105 Cycle Enfield project has been approved for implementation. Construction will now take place over the coming months. The plans will be implemented in a series of phases. Works will be carried out by Ringway Jacobs Ltd on behalf of Enfield Council.

Green Dragon Lane to York Road

Most substantive work is complete.

Borden Avenue to Walnut Grove

Work on the new brick planter has been completed and will be planted shortly. The new crossing adjacent to Regency Court is now open.

 

Sainsbury's junction

Most substantive work is complete.

Station Road / Ford's Grove roundabout

The construction of the brick planters is now complete. The tree pits have been dug and are ready for the arborist for planting when appropriate.

Church Street junction with Bush Hill Road

Most substantive work is complete. Additional seating and benches have recently been installed.

Lodge Drive to Osborne Road

The CCTV column at the junction with Fox Lane has been installed and is awaiting connection. Work on the Park Avenue junction and the adjacent bus stop is now complete. Work is ongoing to install the new footway to the western side of the junction. Work has now also started from Devonshire Gardens towards Aldermans Hill. This work will be undertaken under lane closures and, when required, two way lights.

The section between Hedge Lane and Fox Lane is scheduled, subject to weather conditions, for overnight resurfacing on the week commencing 29 August.

Radcliffe Road to Riverbank

Work on the northbound side is now at the junction with Sherbrook Gardens. The bus build out adjacent to Elm Park Road is complete and open and we are now working towards the shops from Elm Park Road under lane closures.  The new planter is awaiting planting. The island at Firs Lane is awaiting landscaping and tree planting.

Bush Hill to Essex Road

We are working on the final section in front of the parade. The construction of the new planter at Bush Hill is now complete and awaiting planting. Connection of the new crossing and lighting at the Bush Hill junction is imminent. Three new benches have been installed at the junction.

Oaktree Avenue to Highfield Road

Last week we completed the northbound junction and installed the new bus shelters. We are currently working under multi-phase lights and are starting work on the junction with Barrowell Green. Surfacing between Highfield Road and Barrowell Green is scheduled, subject to weather conditions, to be carried out under night-time closures on the week commencing 21 August.

Compton Road Junction

Resurfacing and line marking work has been completed and the junction has reopened. Ongoing work between Pizza Express and Travis Perkins should be completed this week. The cycle stands, signs and posts have been installed and the rain gardens have been planted. The majority of the lighting columns have been relocated and are awaiting connection. Work on the opposite side of the road towards Queen’s Avenue has now commenced.

Ecclesbourne to Aldermans Hill

Work on this section is substantively complete with the exception of the crossing by the Shell garage which is expected to be completed this week.

Bourne Hill junction with Hedge Lane

Work is expected to start in October.

The Triangle

Access to Aldermans Hill from and to Green Lanes has now been closed as per the schedule. We are continuing to remove kerbs and street furniture. Streetlights are being disconnected and removed. Additional work to improve footways on the southbound side has been completed and a bus shelter installed. Work on the kerb line and ducting on the southern side is complete and tactile paving is being installed. The southbound bus boarder has been constructed. The tree pit has been dug out. The central islands along Green Lanes have been removed to allow work outside the Iceland store to begin without additional temporary signals.

 

A possible gas leak and utility issues unrelated to the Cycle Enfield scheme have resulted in an area of the northbound footway being dug up by utility companies.
 

Palmerston Crescent

Most substantive work is complete.

Awaiting decision on whether to proceed to implementation.

A1010 North Corridor Scheme

Why are we doing this

Visit the Project Page

Awaiting decision on whether to proceed to implementation.

High Street – Work at the southern end of the High Street incorporating access works to the Electric Quarter development and pipe installation for energetik’s (http://www.energetik.london/) community heat network to help minimise overall disruption across this busy construction phase has now commenced. The challenging reconfiguration of the Derby Road junction will proceed in the summer holiday period when traffic levels will be lower. The closure of the junction will last 6 weeks to allow the junction to be constructed as quickly and safely as possible. Each of the approach roads will remain open from their opposite ends and diversion signs will be provided. The remaining works on the High Street north of the park will continue until the end of November 2017 but will have a lower impact on traffic.

Block paving on the first roundabout will be completed shortly. All drainage work is now complete. The concrete base of the carriageway has been laid. Work to install specialist kerbing will start shortly. Some footways have been completed and reopened to the public.

Queensway - Associated works have been completed in Queensway to improve pedestrian access to the new school.

Work to construct the bus build out near the Clarence Road junction is now complete. Work on the second bus build out sil start shortly. The Belisha beacon, lamp column and central island on the zebra crossing adjacent to Orchard Road have been removed enabling construction work to continue.
We are awaiting a visit by the National Grid to work on the gas bypass.

Awaiting decision on whether to proceed to implementation.

A1010 South Corridor Scheme

Why are we doing this

Visit the Project Page

Awaiting decision on whether to proceed to implementation.