Enfield Logo

WORK'S ABOUT TO START IN YOUR AREA

Safer Travel, Healthier Choices

We’re making improvements to our neighbourhoods and town centres, creating an environment where many more of us can walk or cycle every day.

 

Over the coming weeks and months construction will start around your area. Even though we plan carefully to minimise inconvenience, there could be disruption to your regular routes, so please bear with us whilst we work to make our borough better for everyone. You can see some of the things we’re doing to minimise inconvenience here.

 

Please note this page will be updated as work progresses on each of the respective schemes.  

Ringway Jacobs have appointed a Public Liaison Officer, Rilwan Oshingbade,to assist with any enquiries related to construction, he can be contacted directly on cyclenfield@ringwayjacobs.com

 

If you have an urgent out of hours please call 0844 967 1611 and the team will try to assist wherever possible. Please be aware that non-urgent issues may be redirected to Rilwan to address during normal office hours.

The A105 Cycle Enfield project has been approved for implementation. Construction will now take place over the coming months. The plans will be implemented in a series of phases. Works will be carried out by Ringway Jacobs Ltd on behalf of Enfield Council.

Green Dragon Lane to York Road

Most substantive work is complete.

Borden Avenue to Walnut Grove

Most substantive work is complete.

Sainsbury's junction

Most substantive work is complete.

Station Road / Ford's Grove roundabout

The construction of the brick planters is now complete. The tree pits have been dug and are ready for the arborist for planting when appropriate.

Church Street junction with Bush Hill Road

Most substantive work is complete.

Lodge Drive to Osborne Road

The CCTV column at the junction with Fox Lane has been installed and connected.

Work was delayed outside the Alfred Herring due to a gas leak unrelated to the Cycle Enfield work which has now been made safe. We are continuing to work on the footway and cycle path as well as working on the southbound footway with the construction of the cycle lane and the disconnection and removal of the lamp posts. Work on the footway to the western side of Fox Lane / Devonshire Gardens has been completed. Work will be undertaken under lane closures and, when required, two way lights.

The signalised crossing is now installed.

 

Radcliffe Road to Riverbank

Work is continuing northbound between Sherbrook Gardens and Green Dragon Lane. Drainage work has been completed as has the kerbing. We are now working on the paving and final bus build-out. Southbound we are now working towards the shops from Elm Park Road under multi-phase lights.  The new planter is awaiting planting. The island at Firs Lane is awaiting landscaping and tree planting. The first phase of surfacing between Station Road to Shrubbery Gardens and Firs Lane and green Dragon Lane is now complete.

Bush Hill to Essex Road

We are working on the final section in front of the parade which should, weather permitting, be completed by the end of the week. Work on the final bus stop is complete and we have now started work on the junctions with Lincoln Road and Village Road under multi-way lights. The remaining surfacing is scheduled, weather permitting, from 25 September for five nights.

Oaktree Avenue to Highfield Road

The surfacing between Barrowell Green and the entrance to Sainsbury’s as well as the junction with Barrowell Green is now complete. We are currently working under two-way lights to complete the final bus build-out.

 

Compton Road Junction

The majority of the lighting columns have been relocated and are connected. Final connections will take place shortly. Work towards Queen’s Avenue on the opposite side of the road to the island is ongoing but is expected to be complete this week and an area of parking has been released back to the public.

Ecclesbourne to Aldermans Hill

Work on this section is substantively complete with the exception of the crossing by the Shell garage which has been installed and is awaiting connection by UKPN. A temporary light has enabled the crossing to be opened while awaiting connection.

Bourne Hill junction with Hedge Lane

Work is expected to start in October.

The Triangle

Access to Aldermans Hill from and to Green Lanes has now been closed as per the schedule. Streetlights are being disconnected and removed.

Additional work to improve footways on the southbound side has been completed and a bus shelter installed. Tree pits have been excavated and area awaiting planting. Work on the kerb line, ducting and tactile paving has been completed near HSBC. Paving to the centre island has been completed. A large amount of footway has been reopened to the public. The kerb line on the opposite side of the island near Barclays Bank has been installed and we have started work on paving the area.

 

We have also started working from the area outside the Inn on the Green towards the final bus stop build out.
 

Palmerston Crescent

Most substantive work is complete.

Awaiting decision on whether to proceed to implementation.

A1010 North Corridor Scheme

Why are we doing this

Visit the Project Page

Awaiting decision on whether to proceed to implementation.

High Street – Work at the southern end of the High Street incorporating access works to the Electric Quarter development and pipe installation for energetik’s (http://www.energetik.london/) community heat network to help minimise overall disruption across this busy construction phase is ongoing. The challenging reconfiguration of the Derby Road junction is now substantively complete and the junction has been reopened. The remaining works on the High Street north of the park will continue until the end of November 2017 but will have a lower impact on traffic.

Excavation work at the front of the shops on the High Street between the library and the Post Office is underway. Kerb laying and block paving work is also taking place in front of the shops to build the parking area and footway,
Some block paving work remains and we are currently excavating the new parking area.

Work to install specialist kerbing has now started. Pedestrian crossing points have been completed and reopened. Some footways have been completed and reopened to the public while work is ongoing on others.

Queensway - Associated works have recently been completed in Queensway to improve pedestrian access to the new school.

A1010 South – Work to construct the third bus build out is underway as is the installation of cycle lane separators an flexible bollards.

National Grid has confirmed they may require several weeks to resolve issues with the gas bypass.

Awaiting decision on whether to proceed to implementation.

A1010 South Corridor Scheme

Why are we doing this

Visit the Project Page

Awaiting decision on whether to proceed to implementation.