Enfield Logo

WORK'S ABOUT TO START IN YOUR AREA

Safer Travel, Healthier Choices

We’re making improvements to our neighbourhoods and town centres, creating an environment where many more of us can walk or cycle every day.

 

Over the coming weeks and months construction will start around your area. Even though we plan carefully to minimise inconvenience, there could be disruption to your regular routes, so please bear with us whilst we work to make our borough better for everyone. You can see some of the things we’re doing to minimise inconvenience here.

 

Please note this page will be updated as work progresses on each of the respective schemes.  

Ringway Jacobs have appointed a Public Liaison Officer, Rilwan Oshingbade,to assist with any enquiries related to construction, he can be contacted directly on cyclenfield@ringwayjacobs.com

The A105 Cycle Enfield project has been approved for implementation. Construction will now take place over the coming months. The plans will be implemented in a series of phases. Works will be carried out by Ringway Jacobs Ltd on behalf of Enfield Council.

Green Dragon Lane to York Road

The zebra crossing is now complete and has been reopened.

 

 

 

Borden Avenue to Walnut Grove

The final section of line marking and cycle segregation units will be installed in the coming week. The bus shelter outside the church has been removed and the new one installed awaiting electrical connection. Three shared parking bays are also currently being constructed and will be completed next week.

Sainsbury's junction

The traffic signals at the junction have been installed and are awaiting final commissioning by Transport for London which is currently scheduled for 28 April. 11 May. Work is expected to be complete by the mid-May.

Station Road / Ford's Grove roundabout

The traffic signals are awaiting final commissioning by Transport for London which is currently scheduled for 11 May. Work is continuing with lane marking, kerb lines and paving slabs. Three central islands have been installed and will be completed in the coming week. Work will continue on the installation of kerb lines, paving work and cycle lane. The work on this section is scheduled to be complete by mid May 2017.

Church Street junction with Bush Hill Road

We are currently constructing additional footpath area behind the bus stops. We will soon be installing a rain garden.

 

Most new street lighting has now been commissioned. Work on this section is expected to be complete by late April.

Lodge Drive to Osborne Road

We will be working between Bourne Hill/Hedge Lane and Fox Lane roundabout in order to install the new cycle path. We will also be installing drainage, paving, signalling and a new bus boarder. More parking spaces have been made available for business customers in this area. The construction of a new bus boarder stop will start next week. Work on this section is scheduled to be completed by late May 2017.

Radcliffe Road to Riverbank

We are installing a new kerb line, cycle lane and paving as well as improving drainage and constructing rain gardens. The work on this section is scheduled to be completed by mid June 2017.

Bush Hill to Essex Road

Work will continue to install new drainage and we will start to build the cycle lane. Work is expected to be complete by August.

Oaktree Avenue to Highfield Road

Work to complete a further bus stop near Fernleigh Road continues. Temporary pedestrian signals will remain place until the new crossing is commissioned.

Compton Road Junction

Work is expected to take place between mid June and late August.

Ecclesbourne to Aldermans Hill

Work is continuing on Palmerston Crescent northbound working north. We will be working on the installation of kerbs, concrete slabs and drainage.  In order to carry out work safely, Broomfield Lane will be closed from Monday 24 April for four weeks.

Bourne Hill junction with Hedge Lane

Work is expected to take place between early July and late September.

Oakthorpe Road to Aldermans

Work is expected to take place between mid June and late July.

The Triangle

Work is expected to take place between mid June and late August.

Palmerston Crescent

Work is expected to take place between mid July and mid August.

Awaiting decision on whether to proceed to implementation.

A1010 North Corridor Scheme

Why are we doing this

Visit the Project Page

Awaiting decision on whether to proceed to implementation.

High Street – The northern section between Eagle House Car Park and Stonehorse Road will be constructed in the first half of the calendar year. The southern section between Stonehorse Road and Clarence Road will be built in the second half of the calendar year. The challenging reconfiguration of the Derby Road junction is being planned for the summer holiday period to minimise disruption.

Queensway - Associated works are planned for Queensway to improve pedestrian access to the new school. The work to improve the footways and add a zebra crossing started earlier this month. This section is not expected to affect the wider traffic network.

Awaiting decision on whether to proceed to implementation.

A1010 South Corridor Scheme

Why are we doing this

Visit the Project Page

Awaiting decision on whether to proceed to implementation.