A105 Project

Here you’ll find updates on construction work along the route. To find out more about the background of this project view the A105 plans page.

View the plans

Keeping you up-to-date

Help with enquiries

If you have an urgent concern with construction works you can call our contractor on 0844 967 1611 (this number is available 24 hours). Please be aware that non-urgent issues may be redirected to the contractors Public Liaison Officer to address during normal office hours.

During normal working hours, Katy Davies, the Public Liaison Officer is available on 07714295768 or cycleenfield@ringwayjacobs.com

If you have a more general question about Cycle Enfield then use our contact page to get in touch.

 

Minimising disruption

We know construction can be disruptive. While there are times when it’s unavoidable, we’re working to make the process more manageable. We have explained the ways we’re working in this minimising disruption PDF guide.

Ongoing work

Hedge Lane Junction

Enfield Council are waiting for works by the gas utility company to adjust a gas main. These works are currently in progress. Once complete, the Council contractor will complete the kerb in this area and then complete full re-surfacing at the junction. This will enable the bus stand to be opened.

Planned work

Snagging

As with any major project, there are a number of snagging issues on-going. Contractors will be completing these works at different places along the route, no significant disruption is expected.